Project Outline
The Ravenhall Outfall Sewer Stage 1A, 1 and 2 consists of approximately 3km of 900mm dia and 1,000mm dia sewer. The delivery of the CWW asset, was a key infrastructure item not only for the project but for the greater area and will be integral to future development works.
As a CWW accredited consultant, DCE weere engaged to complete Civil Engineering and Project Management services with development works including stakeholder liaison and negotiation (with CWW, DEWLP and Department of Transport), master planning and detailed design, tendering, value management and contract formation and administration.