Located near the corner of the Hume Highway and Cooper Street in Somerton, Melbourne Waters 2100mm in diameter Cooper Street Main Drain was constructed diagonally across a 12Ha industrial parcel of land. The drain was constructed along an existing creek in the mid-1980’s.
To accommodate the 1 in 100 year overland flows along the pipe, a 30m wide drainage easement encumbrance was created over the land. DCE were engaged by the owner, Salta Properties to ascertain the feasibility of relocating the existing drain and overland flow path to maximise the value of the property.
Using Infoworks (a dynamic hydraulic modelling software package), DCE presented to Melbourne Water a solution to re-direct the drain around the boundary of the site and by upsizing the pipe to a 2400mm diameter capture the 1 in 100 year overland flows. By eliminating the overland flow path, the drainage easement was reduced to 8m.
DCE also completed the detail design documentation, tendering, contract administration and construction surveillance of the 800 metre long pipeline.
Melbourne Wurundjeri
03 9813 7400
Level 3, 678 Victoria Street
Richmond VIC 3121
info@dceng.com.au
Geelong Wadawurrung
03 5246 1700
60 Moorabool St
Geelong VIC 3220
Brisbane Turrbal
07 3374 9000
Level 14, 167 Eagle Street
Brisbane QLD 4000
Dalton Consulting Engineers acknowledges the Traditional Custodians of country throughout Australia and their connections to land, sea and community.
We pay our respect to their Elders past and present and extend that respect to all Aboriginal and Torres Strait Islander peoples today.